LIVE PROJECT · DROP KERB & VEHICLE CROSSING PERMITS · Scotland · UK-wide

A real AI automation project, phase by phase

The roadmap describes how a project should run. This is one that actually did. Kerbco replaced an eleven-step manual permit chain with a single automated sequence triggered by one enquiry form — and kept a human on the one part that carries a safety consequence.

£0 → £50k

NEW PIPELINE BUILT

11 → 1

MANUAL STEPS PER JOB

£16.90 → £0

MAP COST PER JOB

Minutes

ENQUIRY TO PRICED QUOTE

Measured from the live system. Kerbco is the only client project published on this site.

What happened in each phase

The same five phases as the roadmap, with the real work that sat inside each one.

Phase 0 · Weeks 1–2

Audit the actual chain

We sat with the eleven manual steps behind a single drop kerb enquiry — pricing, permit fee, Street Manager, council reference, utility drawings, operative tickets, compliance pack — and counted what each one cost in hours.

  • A step-by-step map of the enquiry-to-permit chain
  • The £16.90 per-quote map licence identified as a scaling cost
  • Traffic management flagged as work that must stay human

Phase 1 · Weeks 2–4

Foundations: one job record

Everything downstream needed one place to live. Enquiry, pricing inputs, permit reference, drawings, operative credentials and the compliance pack were pulled onto a single job record instead of an inbox and a filing cabinet.

  • One job record every later step reads and writes
  • Operative credential library with expiry dates
  • Council fee and footway build-up rules made configurable

Phase 2 · Weeks 4–9

First automation: enquiry to priced quote

The customer's enquiry form became the only manual data entry in the job. Kerbco prices the crossing from width, footway build-up and the relevant council fee, and issues a real quote in minutes.

  • Automatic pricing and quote issue from one form
  • Permit application fee captured on acceptance
  • Payment set as the trigger that arms the rest of the chain

Phase 3 · Weeks 6–9

The permit chain runs itself

Once the fee is paid, a Street Manager record opens against the job and goes to the council. The returned permit reference lands back on the job and fires the statutory undertaker drawing requests — gas, water, electric, telecoms.

  • Street Manager submission and reference capture
  • Utility drawings requested automatically on permit reference
  • Health & safety, RAMS and reinstatement pack generated per job

Phase 4 · Week 14 onward

Remove the last scaling cost, then run

A mapping engine was built into Kerbco, retiring the £16.90-per-job commercial licence and taking the marginal cost of quoting to zero — which is what made high-volume quoting viable at all.

  • In-house mapping engine replacing a paid licence
  • Marginal cost of a quote reduced to zero
  • Ongoing monitoring and tuning of the live chain

What deliberately stayed human

Traffic management design

Signage, coning and pedestrian routing are drawn by hand in Roadplan. It produces both the council submission plan and the crew's on-site sign install sheet — and it is the one part of the job where a wrong call has a safety consequence.

Anything a council sees for the first time

An incomplete submission goes to the back of a four-to-eight week queue. Operatives with a lapsed ticket simply cannot be attached to a submission, so a human never has to catch that manually.

"I put the job in once. By the time I've made a coffee the quote is out, and once they accept, the permit, the drawings and the paperwork all handle themselves. The only thing I actually draw is the traffic management — and that's the bit that should have a human on it."

Operations — Kerbco — drop kerb permit contractor

Common questions

Is this a real, live AI automation project?

Yes. Kerbco is a working drop kerb and vehicle crossing permit operation, and the chain described here runs its live jobs. It is the only client project published on this site — every other page describes capability, not customer results.

How long did the project take end to end?

Enquiry-to-permit chain live in 9 weeks; mapping engine replaced the paid licence at week 14.

What is still done by hand?

Traffic management design. Signage, coning and pedestrian routing are drawn manually, producing both the council submission plan and the crew's sign install sheet. Everything else in the eleven-step chain runs automatically.

Would a project like this work for my business?

The pattern transfers wherever one enquiry triggers a long chain of dependent admin steps across several systems. The £499 AI Ops Audit maps your chain the same way and tells you what the first phase would actually cost before anything is built.

Map your own chain

A 20-minute discovery call is the fastest way to find out whether your business has the same shape of problem — one enquiry triggering a long chain of dependent admin.