ENERGY & DATA-CENTRE CIVILS// Central Belt, Scotland// 120 staff · £24m turnover

Programme intelligence for a data-centre build: cutting re-plan time from days to minutes.

NorthGrid Infrastructure · Eleki + NoPrint · Integrated into live project in 10 weeks

2 days→15 min

RE-PLAN TIME

↓63%

PROGRAMME SLIPPAGE

1

SOURCE OF TRUTH

£420k

AVOIDED OVERRUN

THE CHALLENGE

  • Programme slippage on a £40m data-centre build was being discovered weeks after it started.
  • Site reports, dockets and plant logs lived in five different systems — none of them talking to each other.
  • Re-planning a single delay was eating two days of senior engineering time.

THE SOLUTION

  • Eleki ingested live signals from dockets, plant GPS, weather feeds and supplier ETAs into one model.
  • AI scheduling proposed minimal-impact re-plans the moment a slippage signal hit a threshold.
  • Project directors approved or overrode recommendations from a single mobile-friendly dashboard — humans in the loop on every decision.

"We used to find out about slippage in the weekly meeting. Now we find out the same hour it happens — and the system has already drafted the fix."

Rachel StewartProject Director, NorthGrid Infrastructure

OPERATOR QUESTIONS

How this actually works day to day

Does the AI change the programme on its own?+

Never. Eleki drafts a minimal-impact re-plan and shows the trade-offs; a project director approves, edits or rejects it. Every decision is attributed to a named person with a timestamp.

What data does it need to detect slippage early?+

Dockets, plant GPS, supplier ETAs and weather feeds. Those four signals were already being produced on site — the change was routing them into one model instead of five disconnected systems.

How does this sit alongside the main programme software?+

It sits above it. The client's planning tool remains the contractual programme of record; Eleki provides the live intelligence layer and pushes approved changes back rather than replacing the planner.

Is the audit trail good enough for a client or NEC compliance conversation?+

Yes. Every signal, recommendation, approval and override is logged with its source data, which is what makes early-warning notices and compensation-event evidence straightforward to assemble.